Once a table is opened, you can assign data to the lithology log in the borehole view. First, switch back to the borehole view by clicking the appropriate Borehole tab or by clicking the Borehole 1 object in the View Manager.
To assign data to the lithology log:
Click on the lithology log in either the view window or the Object Manager.
In the Property Manager, click on the Log tab.
The Lithology table field is blank. Click in the blank box and select Lithology from the list. This is the table that was just opened.
Next to the Lithology keyword column option, click in the blank box and select Lithology Keyword.
Next to the Indent percentage column option, click on [Unspecified] and select Indent Percentage.
Next to the Indent keyword column option, click on [Unspecified] and select Indent Keyword.
Next to the Indent line scale column option, click on [Unspecified] and select Indent Line Scale.
At this point, the log is ready to be activated.
Back to Opening Data
Next to Activating the Borehole