Activating the Borehole - Tutorial

Once the lithology log properties are assigned, you can activate the borehole by selecting a borehole name. When a borehole name is selected, the data are linked to the borehole design. If there are multiple items in the borehole, each of the items must have tables and columns specified before activating the borehole.

 

To activate the borehole:

  1. Click the View | Display | View Properties command.

  2. In the Property Manager, click on the View tab.

  3. Next to the Hole ID Filter option, click on the word -Empty- and select DH-1 from the list.

  4. Activate the borehole by changing the View mode to Active mode in the Property Manager. You may also click the Log | Display | Design Mode command or press F4 on the keyboard.

 

The borehole is active, and the log displays empty fill patterns for each block. This is because fill patterns have not yet been set for the lithologies.

 

Back to Attaching a Table to the Design

Next to Creating a Lithology Scheme